Clause Library  /  FAR Part 46
FAR 52.246-6

Inspection—Time-and-Material and Labor-Hour

A contract clause under the Federal Acquisition Regulation, placed in Uniform Contract Format Section E (Inspection and acceptance).

Contract clausePrescribed in 46.306UCF Section EIncorporated by reference

When it applies

Required by FAR 46.306 for noncommercial time-and-materials and labor-hour contracts.

Prescription

The FAR directs use of 52.246-6 at 46.306read the prescribing section on acquisition.gov →.

Official text

The full, authoritative text of 52.246-6 is on acquisition.gov: View FAR 52.246-6 →

Frequently asked questions

When does FAR 52.246-6 apply?

Required by FAR 46.306 for noncommercial time-and-materials and labor-hour contracts.

Where is FAR 52.246-6 prescribed?

The FAR prescribes 52.246-6 at 46.306. ArcClause selects it automatically when your acquisition triggers that prescription.

Is FAR 52.246-6 a solicitation provision or a contract clause?

52.246-6, Inspection—Time-and-Material and Labor-Hour, is a contract clause under the Federal Acquisition Regulation.

Is FAR 52.246-6 incorporated by reference or set out in full text?

52.246-6 is typically incorporated by reference in the contract.

Where can I read the official text of FAR 52.246-6?

The full, authoritative text of 52.246-6 is published on acquisition.gov.

How do I know which clauses apply to my acquisition?

ArcClause builds a complete FAR/DFARS clause matrix for your acquisition automatically — enter your parameters and it selects every applicable provision and clause, including 52.246-6 when triggered. It is free to use at https://www.aframesolutions.com/arcclause.

Get a free alert when FAR 52.246-6 changes. New or revised text, or a FAR Overhaul deviation — we'll email you when it happens. No spam, unsubscribe anytime.

Which clauses does your solicitation need?

Answer a short wizard and ArcClause builds your full FAR & agency-supplement matrix — with the prescription behind every row. Get it emailed to you as Word & Excel, and we'll alert you when a clause in it changes during the FAR Overhaul. Free, no login.

Build your matrix →