The short answer: Two source selection stories landed in November 2026. GAO's FY2026 bid protest report showed the lowest sustain rate in five years, 10%, but half of protesters still got some relief, mostly because agencies took corrective action before GAO ruled. The most common reasons GAO sustained a protest were an unreasonable technical evaluation, an unreasonable past performance evaluation and a flawed selection decision. Meanwhile, the Army paid a losing protester's legal fees after AI evaluations generated during a live $449.4 million competition were left out of the record. Both stories teach the same lesson: protests are decided by the record, and the record has to show the evaluators' own judgment, tied to the proposal.

10%
Sustain rate on merit decisions in FY2026, down from 14%
50%
Effectiveness rate: protesters who got some relief
1,587
Cases filed, down 6% from FY2025

What GAO reported

Each year the Competition in Contracting Act requires GAO to report its protest numbers to Congress, along with the most common reasons it sustained protests. The FY2026 report (GAO-27-900747) covers October 2025 through September 2026.

FY2026FY2025FY2024FY2023FY2022
Cases filed1,5871,6881,8032,0251,658
Merit decisions412380386608455
Sustains43536118859
Sustain rate10%14%16%31%13%
Effectiveness rate50%52%52%57%51%

Of the 1,587 cases, 1,500 were protests, 34 were cost claims and 53 were requests for reconsideration. Of the 1,600 cases GAO closed, 292 involved task orders. GAO issued every decision within its 100-day deadline. It also notes that the 43-day funding lapse at the start of the fiscal year coincided with a drop in filings: 318 cases in the first quarter, against a four-year average of 474.

Why 10% is the wrong number to plan around

The sustain rate only counts protests GAO decided on the merits. Many protests never get that far, because the agency takes corrective action first: it re-evaluates, rewrites the decision or reopens the competition. GAO says plainly that agencies don't report why they do this. The effectiveness rate captures those cases, and it has sat between 50% and 57% for five years.

For a contracting officer, a protest that ends in corrective action still costs weeks, a stop-work and a second evaluation. Whether the protest succeeds is decided by the record the team built before award.

The three reasons GAO sustained protests

1. A technical evaluation that contradicts its own findings

GAO's example is DAS Federal, LLC (B-424464 et al., July 31, 2026). Evaluators found several strengths and no weaknesses in the protester's quotation. The agency still rated it "some confidence" and said the approach yielded no benefits. GAO found that unreasonable.

The lesson is not about rating scales. A rating has to follow from the findings written down beside it. When the consensus rationale and the findings point in different directions, the record argues against itself. Before the consensus is final, the chair should read each rating next to its findings and ask whether a stranger would reach the same rating from them.

2. A past performance evaluation that skips what the solicitation allowed

In Veterans Management Services, Inc. (B-424182.2, B-424182.3, June 22, 2026), the solicitation let the agency consider CPARS data more than three years old. The agency then failed to evaluate the protester's past performance information that was more than three years old.

Recency and relevance rules belong in the solicitation. Once written, they must be applied the same way to every offeror. A short check before award helps: for each offeror, list the references considered and the ones set aside, with the reason in the solicitation's own terms.

3. A selection decision built on a missed threshold check

In Morrish-Wallace Construction d/b/a Ryba Marine Construction Co. (B-423796.2, Feb. 5, 2026), the agency found the awardee's bid responsive although the awardee had not acknowledged the third amendment, which added material requirements. The selection decision rested on a finding the record could not support.

Amendment acknowledgments are easy to miss when a solicitation has been amended several times. They belong on the pre-award checklist, checked for the apparent awardee before the decision document is signed.

The Army's AI protest: what happened at White Sands

The second story is TRAX International's protest of an Army award at White Sands Missile Range. The Army said its evaluators did not rely on AI. Court filings later showed AI evaluations of all three proposals had been generated during the live competition and left out of the record.

The contract is a cost-plus-fixed-fee award for mission and engineering support at the White Sands Test Center in New Mexico. The Army awarded it to Southwest Range Services, the incumbent, at an evaluated price of $449.4 million. TRAX International proposed about $420 million. Both offerors received Outstanding overall ratings, and Southwest Range was rated higher on continuity of operations.

Why the record, not the AI, was the problem

The court did not hold that using AI was improper, and TRAX did not win on the merits. What cost the Army was the record. The government's account of who saw the AI output and when changed as declarations came in, and AI evaluations generated during a live competition were left out of the file until a judge ordered them in.

Commentators drew two lines from the case. Bradley's government contracts team put the first one plainly: "an agency's consideration of an AI evaluation is not the same thing as its reliance on that evaluation." The second runs the other way. If AI output that was generated during the evaluation is missing from the record, the agency can't show which of the two it was. In its summary of the opinion, Robinson+Cole notes the court found the AI evaluations were generated during the decision-making process. For one offeror, passages of the board's final evaluation were "nearly identical, sentence for sentence," to the AI evaluation.

What the proposed FAR Part 15 rewrite changes, and what it doesn't

The FAR Council's proposed rule for Parts 8, 12, 13, 15, 38, 44 and 51 (FAR Case 2026-003) was published September 18, 2026, and its comment period closed October 19. It is still a proposed rule. As written, it would:

No FAR rule, current or proposed, addresses AI in proposal evaluation. Read against GAO's three sustain grounds and the TRAX case, the proposal changes how agencies talk to offerors. It doesn't change what a reviewer will look for in the record, whether or not AI was involved. Past performance must still be evaluated "consistent with the terms of the RFP," including currency and relevance. The decision must still be the source selection authority's own comparative judgment.

A pre-award check built from both stories

For offerors, the practical step from the TRAX case is to ask at a debriefing whether proposal-specific AI reports were generated, when, and who received them.

Where A-Frame One fits

In A-Frame One Select, the AI Assistant suggests strengths and weaknesses only when the evaluator asks, and each one points to the proposal page it came from. The AI cannot save anything. The evaluator checks the cited page, then keeps, edits or dismisses each suggestion, picks the rating and writes the rationale. Each technical finding has to cite the proposal and solicitation pages it rests on before it can be saved. The consensus view shows how each evaluator rated every factor, and completing the consensus locks it and exports it to Word for the record. The award decision memo is drafted in Compose from those exports as suggestions, and the source selection authority writes the tradeoff. The source selection walkthrough shows each step.

For the FY2025 numbers and the longer trend, see GAO Bid Protest Trends FY2025.

Sources

Common questions

What was GAO's bid protest sustain rate in fiscal year 2026?

10% of protests decided on the merits, the lowest in five years. GAO sustained 43 of 412 merit decisions, down from 14% in FY2025 and 16% in FY2024.

What is the effectiveness rate?

It counts every protest where the protester got some relief, either because the agency took corrective action or because GAO sustained the protest. It was 50% in FY2026, against 52% in FY2025.

What were the most common reasons GAO sustained protests in FY2026?

An unreasonable technical evaluation, an unreasonable past performance evaluation and a flawed selection decision, in that order.

Did the court find the Army's use of AI improper?

No. The Court of Federal Claims denied TRAX's protest on September 22, 2026, because TRAX could not identify an actual evaluation error traceable to the AI tool. The court did order the AI evaluations added to the administrative record.

Do AI outputs belong in the source selection record?

In this case the court ordered AI evaluations generated during the evaluation added to the administrative record, even though the Army said evaluators did not rely on them. If an AI tool produced anything about a live proposal, keep it in the contract file with who received it and when.

Does the proposed FAR Part 15 rewrite lower the documentation requirement?

No. As proposed, agencies must evaluate proposals based solely on the factors and subfactors in the RFP and document the evaluation, and the source selection decision must be documented with the rationale for any tradeoffs. The decision does not need to quantify the tradeoffs.

Run your next source selection on one record.