The short answer: PALT (procurement administrative lead time) is the number of days between the date an agency issues the initial solicitation and the date of award. OFPP set that definition for contracts and orders above the simplified acquisition threshold. Many contracting offices also count from the day they accept the requirement, because that is the part of the timeline they control. To shorten PALT, track it on every action, set a target by type of buy, and look at the actions closest to their target first, not at the office average.
Every contracting office gets asked how long it takes to buy something. PALT is the number that answers it. It is also one of the few acquisition metrics that leadership, the program office and the contracting office all care about, for different reasons.
The trouble is that most offices see PALT once a quarter, as an average, after the awards are already made. By then the number can only explain what happened. It cannot change it.
Section 878 of the FY2019 National Defense Authorization Act told the Office of Federal Procurement Policy (OFPP) to define PALT and to plan how agencies would measure and report it. OFPP proposed the definition in the Federal Register on January 21, 2020 (85 FR 3428):
"The time between the date on which an initial solicitation for a contract or order is issued by a Federal department or agency and the date of the award of the contract or order."
OFPP, Procurement Administrative Lead Time, 85 FR 3428The definition covers contracts and orders above the simplified acquisition threshold. It has special start dates for cases without a normal solicitation. For an unsolicited proposal, the clock starts when the government tells the offeror it accepted the proposal. For a broad agency announcement, it starts when the final combined synopsis and solicitation is issued. The data comes from the solicitation date field in FPDS, which became mandatory for these actions in June 2019.
The official clock starts at the solicitation. But a large share of the calendar goes by before that: the package comes in, the contracting office reviews it, sends it back, and the program office fixes the statement of work and the cost estimate. None of that time shows up in the official number.
That is why many offices keep a second count that starts when the contracting officer approves the requirement. It is the measure the office can act on. If you track both, label them clearly, so nobody compares one office's internal PALT with another office's official PALT.
An office average of 110 days says nothing about the three actions that are at day 95 with a 100-day target. Those are the ones that need attention this week. Three changes make PALT something you can manage, not just report:
Near the end of an action, the work is mostly documentation. The contracting officer compares the price proposals with the government estimate and writes up the price analysis. Then the same numbers go into the award decision memo. Then the clause matrix gets checked against the solicitation. Each step moves numbers from one document to the next, and each retyped number is a chance for an error that sends the file back.
This is where software helps the most. When the estimate, the proposals and the memo live on one record, the memo can be drafted from the record and the price analysis instead of retyped. The decisions stay with the contracting officer: whether the price is fair and reasonable, what goes in the memo, which clauses apply.
The demo above follows one action with 4 days left to its target. A-Frame One Tracker counts PALT on each requisition from the day the contracting officer approves the requirement, and a custom dashboard sorts the actions by how close they are to their target.
PALT goes down when the office sees each action's clock while there is still time to act, and when the last steps stop depending on retyped numbers. The official definition tells you what to report. The internal count tells you where to look on Monday morning.
PALT stands for procurement administrative lead time. It measures how long the government takes to award a contract or order.
Under the OFPP definition, the clock starts on the date the agency issues the initial solicitation and stops on the date of award. Many contracting offices also track an internal count that starts when the contracting officer approves the requirement, because that captures the package review time the official measure leaves out.
Contracts and orders above the simplified acquisition threshold. The definition also sets special start dates for unsolicited proposals, broad agency announcements, and orders under IDIQ contracts with pre-priced line items.
It depends on the type of buy. A simplified acquisition and a full source selection should have different targets. Set the target on each action from its type, then sort actions by how close they are to it.
No. In A-Frame One the AI drafts the price analysis summary, the award decision memo and the clause answers as suggestions. The contracting officer decides whether the price is fair and reasonable, what goes in the memo and which clauses apply.
Track each action's clock, sort by days to target, and draft the last documents from the record.